SST warehouse and office project is built in Long An, which is an important traffic hub connecting directly between the Mekong Delta and Ho Chi Minh City.

For this project, Dinco E&C is the General Contractor, with the supervision consultancy by Pure Vietnam Co., Ltd. and concept design consultancy by HaskoningDHV Vietnam originated from the Netherlands.

Currently, Dinco Site Management Board has completed 50% of the work volume at the project, although the epidemic situation is complicated, the Site Management Board team has prepared the best plans to expeditiously complete the project in October this year.